2. Prepare the Drain Location
IMPORTANT! For installation on a concrete floor, clearance for the drain assembly must be provided.
Refer to the template provided with the bath.
Provide access for making the final drain connection from below.
Verify adequate drain clearance so the bath will install properly.
1-1/2"
(38 mm)
Finished Floor
Gasket
Frame
Bath